Meadow Gold Demolition Project Update

If you have driven down I-74 lately, you probably noticed some significant changes to the Meadow Gold Demolition site. The Public Works staff can now see businesses on the north side of I-74 from the back of the Public Works facility. The walls and above ground support structure of the existing building are gone, leaving the old building floor exposed to the elements. Homrich’s crew has started the process of removing the floor slabs, and they anticipate beginning the demolition of underground foundations and piping the week of September 13. They continue to stay on schedule for completion by the end of October. Below are several pictures of the floor slab from what used to be the interior of the building.