John Street Watershed Drainage Improvements

Work Complete. Work on John Street in the Randolph-Neil block has been substantially completed.

Work In-Progress. Installation and backfill of the 60-inch storm sewer on John Street to approximately ½ block west of Randolph Street is complete. Fiber optic and electrical conduit installation is taking place on John Street in the State-Randolph block and should be complete early next week. Preparation of the pavement sub-grade on John Street in the State-Randolph block will begin once the fiber optic and electrical conduit work is complete.

Street Closures and Traffic Control. John Street between State Street and Randolph Street remains closed to through traffic. Traffic on State Street and Randolph Street will continue to be narrowed to one lane in each direction during this phase of the project.

Project Progress on the John Street Drainage Improvement Project.