2010 Infrastructure Maintenance

Annual Alley Maintenance
Feutz completed paving of the alley bounded by 5th, 6th, Church, and Park Streets. They continue to work paving the alley bounded by 4th, 5th, Eureka, and Tremont Street.

Pavement Marking Removal and Installation 2010 Project
Pavement marking removal and installation is complete on the following locations:

  • Staley Road at Springfield Avenue
  • State Street

Currently, Varsity Striping and Construction Company is working on the following locations:

  • Randolph Street
  • Church Street

All streets will remain open to traffic throughout the pavement marking removal and installation processes, although lanes may periodically be closed as necessary during working hours.