Work Complete. Installation of the 60-inch storm sewer on John Street between State Street and Randolph Street is complete. Fiber optic and electrical conduit installation is also complete on this block.

Work In-Progress. Pavement restoration is in progress and is approximately 1/3 complete on John Street between State Street and Randolph Street.

Street Closures and Traffic Control: John Street between State Street and Randolph Street will continue to be closed to through traffic. Traffic on State Street and Randolph Street remains narrowed down to one lane in each direction during this phase of the project.