John Street Watershed Drainage Improvements

Work Complete. Roadway pavement and curb/gutter are complete on John Street between State Street and Randolph Street.

Work In-Progress. Sidewalk and driveway installation continues on John Street between State Street and Randolph Street. This work is expected to be completed by early next week. On Monday, October 11, installation of the 60-inch storm sewer will start on John Street between Prairie Street and State Street.

Street Closures and Traffic Control: All lane restrictions have been removed from Randolph Street in the vicinity of John Street. Starting Monday, October 11, John Street will reopen between State Street and Randolph Street. Also starting Monday, October 11, John Street will be closed between Prairie Street and State Street. Traffic on State Street will remain narrowed down to one lane during this phase of the project.