Boneyard Creek – Second Street Reach

O’Neil Brothers is concentrating on completing the construction of the basin south of White Street. Most of the landscaping and concrete work has been installed in the basin south of White St. O’Neil Brothers has completed the construction of the MSE wall north of White Street. This allows for the completion of the earthwork and landscaping in that area. The rain garden along University Avenue has been installed and is functioning. Due to the time of the year, some of the landscaping in the north basin may be installed next spring, but all of the infrastructure will be installed this construction season. The project is on schedule and within the budget.