Boneyard Creek – Storm Sewer Improvements

The installation of the 8’x6’ box culverts has been completed east of Neil Street along Logan Street. Feutz Contractors is continuing the construction of the 8×6 box down Clark Street towards Randolph Street. At Randolph we will be installing a high capacity grate to intercept the storm water flowing east down Clark Street. The project will turn south down Randolph to White Street. At White Street, a high capacity grate will be installed. The project is on schedule and within the budget.