John Street Watershed Drainage Improvements

Work Complete: Installation of the 60-inch storm sewer was completed this week between Prairie Street and State Street. This completes the installation of all 60-inch storm sewer on the project.

Work In-Progress: Work continues between Prairie and State on the installation of sanitary service connections, storm inlet installation and other smaller underground conduit work. Backfilling and pavement restoration is also underway on this section. The entire project is will be complete within the next few weeks.

Street Closures and Traffic Control: John Street continues to be closed between Prairie Street and State Street. Traffic on State Street also continues to be narrowed down to one lane at John Street.

Project Progress on the John Street Drainage Improvement Project: