John Street

With unbelievable weather cooperating with the project, O’ Neil Brothers has arrived at the project terminus, Daniel and Willis. The intersection of Willis and Daniel cannot be closed until the intersection of John and Willis is open to traffic. Due to this contractual restriction, the contractor will not be able to complete the storm sewer for about three weeks. Concrete crews have begun construction of the John Street pavement west of Prospect Avenue. Landscaping will begin mid April and should be complete about a week later. The project is on budget and on schedule for a June 2012 completion.