John Street

With unbelievable weather still cooperating with the project, O’ Neil Brothers has arrived at the project terminus, Daniel and Willis. The contractor will not be able to complete the storm sewer in about one week. The intersection of Willis and Daniel cannot be closed until the intersection of John and Willis is open to traffic. Concrete crews have completed construction of the John Street pavement west of Prospect Avenue to Willis Avenue and may open John Street early next week, weather dependent. Landscaping will begin within the next few weeks and should be complete about a week later. The project is on budget and on schedule for a June 2012 completion.

John Street ImprovementsJohn Street Improvements