O’Neil Brothers has completed a major project milestone, they have completed all of the pavement and sidewalk along the project. O’Neil Brother’s subcontractor, JF New, is working on planting the final rain gardens along Willis Avenue. During the week of June 4, JF New will complete grading and seeding along the entire project parkway. Landscaping is generally one of the final items to be completed and tends to generate a number of resident questions and concerns. During the project, a design change was made to change the sidewalk from pervious concrete to a pervious brick. The project is on budget and on schedule for a June 2012 completion.