2012 Concrete Street Maintenance

Plymouth Drive
Duce Construction has completed all of the pavement, curb and sidewalk repairs on Plymouth Drive from Harrington Drive to Devonshire Drive. Duce’s sub-contractor will lay sod over the next few weeks.

Harris Avenue
Duce Construction has completed all of the pavement patching, curb and sidewalk repairs on Harris Avenue from Bradley Avenue to Maple Street. Duce’s sub-contractor has begun preparing lawns for the laying of sod and should complete the work over the next few weeks.

Research Road
Duce Construction continues to work on the pavement replacement on Research Road. Duce has started work on phase four. There are six phases of work total. Due to multiple utility conflicts at the intersection of Research Road, Newton Drive and Newmark Drive, the progress of work has been delayed by at least one week. The original completion date for Research Road is September 30.