Healey Street Construction Update

A&R Mechanical Services, Inc. has continued to work at the intersection of Sixth St. and Healey St. They have completed reconstruction of the northeast corner of the intersection, and they should finish reconstruction of the west half of the intersection this week. A&R is also nearly done reconstructing the east half of 500 block of Healey St. They are currently on schedule to be substantially complete by August 15, 2014.