Fire Station 3 Addition Construction Update

Stronghold Construction Inc. of Monee, IL continues to make progress on the construction of the Fire Station 3 Addition project. In the past two weeks, they have poured the interior floor slab, and they have started the process of laying the exterior brick. Stronghold’s masonry subcontractor should complete the exterior brick work this week if the weather permits. Over the next two weeks, Stronghold’s trades subcontractors will begin the interior finish work. The project is on schedule for completion by the end of July 2015.

 

 

 

FS3 3

 

FS3 2

FS3 1