2012 Concrete Street Maintenance

Plymouth Drive Duce Construction has completed all of the pavement, curb and sidewalk repairs on Plymouth Drive from Harrington Drive to Devonshire Drive. A few items (punch list) of work remain. Lawn restoration will be done in September. Harris Avenue Duce Construction will complete all of the pavement patching, curb and sidewalk repairs on Harris…
(Read the Rest…)

Town Center Blvd

Cross Construction has completed the concrete work for the project. Champaign Signal and Lighting, Inc. are working on the installation of the traffic signals at Moreland & Town Center and the streetlights along Town Center. The project is on schedule and on budget for a fall completion date.

South Fourth Street

Stark Excavating, Inc. continues to make great progress towards overall completion of the South Fourth Street Project. They have completed the base course widening along the south side of Windsor Rd and have started along the north side. Stark has completed the main line storm sewer along Fourth Street and has completed 70% of the…
(Read the Rest…)

Neil Street Sanitary Sewer Improvements

Construction of the proposed sanitary sewer replacement of the Boltini/Hyatt Place Alley sanitary sewer closed Neil Street between Church and Park on Monday, July 23. Excavation in Neil Street for manhole installation encountered a larger than expected electrical vault that the existing downstream sanitary sewer curled around with multiple elbows. Concrete encasement of the existing…
(Read the Rest…)

2012 Concrete Street Maintenance

Plymouth Drive Duce Construction has completed all of the pavement, curb and sidewalk repairs on Plymouth Drive from Harrington Drive to Devonshire Drive. A few items (punch list) of work remain. Lawn restoration will be done in September. Harris Avenue Duce Construction has completed all of the pavement patching and curb repairs on the south…
(Read the Rest…)