Category: Public Works Department News

September Service Requests

A total of 316 service requests from citizens and City staff were recorded during September 2012 in the Public Works’ Department. This was a decrease of 400 requests (-56%) from the previous month’s count of 716. The chart below tracks the number of requests recorded each day by staff. Calmer weather in September was the…
(Read the Rest…)

Fourth Street

Last week, we were able to construct approximately 2255 LF of Fourth Street before the rains stopped the paving operations. Stark Excavating was able to complete the final 1790 LF of the southbound lane of Fourth Street on Tuesday. Stark Excavating will now begin working on connecting the Fourth Street pavement to St. Mary’s Road….
(Read the Rest…)

2012 Sanitary Sewer Rehabilitation and Improvements Project

This project was awarded at the July 5 City Council meeting and consists of rehabilitating various sanitary sewers and appurtenances located throughout the City. It includes a total of approximately 800 lineal feet of new sanitary sewer installed by Horizontal Directional Drilling in the south 500 block of Lynn Street neighborhood and “upsizing” approximately 280…
(Read the Rest…)

Glenn Park Drive Public Input Meeting – September 27, 2012

As part of the ongoing City efforts to elicit public comments on the  West Washington Street Drainage Improvements, a meeting was held on-site at Glenn Park on September 27 to allow nearby residents to see and discuss several concept plans for the proposed Glenn Park Detention basin facilities. City staff along with the project consultant…
(Read the Rest…)