Category: Public Works Department News

July Service Requests

After a very busy June, the Public Works Department saw a decrease in service requests submitted during the month of July. Citizens and City staff submitted 423 total requests during July 2013. This count decreased by 517 (-122%) compared to the 940 requests that were received in June. The chart below tracks the number of…
(Read the Rest…)

Green Street Road Closure

In order to install a new sanitary sewer connection at 112 E. Green Street, Broeren Russo and Mayfield Construction will be closing all lanes of Green Street between First Street and Second Street from Monday, August 12, 2013, to Thursday, August 15, 2013. This repair requires an excavation into the middle of the street in…
(Read the Rest…)

Market Street

Cross Construction continues to make excellent progress on completing the infrastructure improvements to Market Street from Kenyon Drive to Olympian Drive. Cross Construction is currently working on re-grading the existing ditches along Market Street. Champaign Signal is working on the installation of new streetlights. The work is on schedule for a fall completion date.

Fourth Street

Stark Excavating continues to make progress towards the project completion, although rains have delayed some work. Stark is currently working on the placement of the topsoil and grading for seeding along 4th Street and completing project sidewalks. The project is on schedule and on budget for a fall completion date in 2013.

IDOT Windsor Rd. and I-57 Bridge Project: Traffic Switchover and Interstate Closure No. 3

Work on Stage 1 of IDOT’s Windsor Road Bridge project over Interstate 57 is nearing completion and IDOT and their contractor, O’Neil Brothers Construction, is expecting to begin Stage 2 of the project. In preparation for starting Stage 2 work, they will be closing the north side of the bridge and will switch all traffic…
(Read the Rest…)

Page 16 of 41« First...10...1415161718...3040...Last »