The Public Works Department hosted their Biennial Public Works Kids’ Day on June 5, 2012. This activity stems from celebrating the APWA Public Works Week to recognize Public Works’ staff for work they do throughout the year. This event gives children, grandchildren, nieces, and nephews of Public Works’ employees an opportunity to experience firsthand the…
(Read the Rest…)

John Street

O’Neil Brothers has completed a major project milestone, they have completed all of the pavement and sidewalk along the project. O’Neil Brother’s subcontractor, JF New, is working on planting the final rain gardens along Willis Avenue. During the week of June 4, JF New will complete grading and seeding along the entire project parkway. Landscaping…
(Read the Rest…)

Town Center Boulevard Improvements – Start of Construction

Cross Construction, Inc. began construction activities for improvements along Town Center Boulevard between Neil Street and Ryder Lane this week. The project includes: A traffic signal at the intersection of Moreland Boulevard and Town Center Boulevard. An eastbound left turn lane from Town Center onto northbound Moreland. A westbound left turn lane from Town Center…
(Read the Rest…)

John Street

O’Neil Brothers is near the terminus to the John Street Drainage Improvement Project, Daniel and Willis Street. Over the last couple of weeks, the new storm sewer system has worked as designed and prevented flooding at the intersection of Daniel and Willis. Pavement has been constructed to the final intersection of Daniel and Willis. Remaining…
(Read the Rest…)

Staley Road Project

The Staley Road Project is currently slightly ahead of schedule for stage 1 (Springfield Avenue – Route 10 to Bradley Avenue). Patching is complete and Open Road Paving Company continues to work on pipe culvert extensions, sidewalk ramps, pipe under drains, concrete curb and gutter, full depth road widening, and earthwork items. Later next week,…
(Read the Rest…)

2012 Slurry Seal Project

AC Pavement Striping Company is on schedule and will complete the Slurry Seal Project on Friday, May 18 (providing any unforeseen events). The project has concentrated work on the oil and chip type streets south of Church Street and east of Prospect Avenue and will seal approximately 17 lane miles of City oil and chip…