Curtis Road Lane Closure Extension

A&R Services has closed a westbound lane of Curtis Road between Cherry Hills Drive and Marjorie Lane in order to complete a gas repair. The lane closure began on Monday, June 15, 2015. The lane closure duration has been extended. The lane will now be reopened on Friday, June 26, 2015. Westbound traffic will be…
(Read the Rest…)

Neil Street Lane Closure

In order to perform electric work, Ameren Illinois will close a lane of Neil Street between Columbia Avenue and Washington Street. The lane closure will begin on Monday, June 22, 2015, and will reopen on Thursday, June 25, 2015. One lane of northbound and one lane of southbound traffic will remain open throughout the work….
(Read the Rest…)

Olympian Drive – Street Construction

The Illinois Department of Transportation (IDOT) has awarded a contract to Feutz Excavating of Paris, Illinois, to construct a new section of Olympian Drive from west of Champion Drive to Duncan Road, including the reconstruction of the intersection of Duncan Road and Olympian Drive. The proposed improvement consists of a new PCC pavement, PCC sidewalks,…
(Read the Rest…)

Fire Station 3 Addition Construction Update

Stronghold Construction Inc. of Monee, IL continues to make progress on the construction of the Fire Station 3 Addition project. In the past two weeks, they have poured the interior floor slab, and they have started the process of laying the exterior brick. Stronghold’s masonry subcontractor should complete the exterior brick work this week if…
(Read the Rest…)

Curtis Road Construction (at Staley Road)

In order to perform a gas repair, A&R Services will be excavating near the intersection of Curtis Road and Staley Road. The construction will begin on Monday, June 22, 2015, and will reopen on Friday, June 26, 2015, weather permitting. All directions of traffic will remain open during this construction; however, westbound traffic will be…
(Read the Rest…)

Country Fair Drive Lane Closure (Emergency Pavement Repairs)

In order to repair pavement failures, Feutz Contractors closed the southbound lane of Country Fair Drive between Bradley Avenue and Camp Drive today to complete concrete cutting.  Feutz will complete the work by laying rebar and new concrete on Thursday, June 18, which will require an additional closure of the southbound lane. Flaggers will be…
(Read the Rest…)

Curtis Road Lane Closure

In order to perform a gas repair near the intersection of Curtis Road and Cherry Hills Drive, A&R Services have closed a westbound lane of Curtis Road between Cherry Hills Drive and Marjorie Lane. The lane closure began on Monday, June 15, 2015, and will reopen on Friday, June 19, 2015, weather permitting. Westbound traffic…
(Read the Rest…)

Mattis Avenue Street Construction

The City of Champaign has awarded a contract to Stark Excavating of Bloomington, Illinois. This work will reconstruct Mattis Avenue from south of Curtis Road to south of Congressional Way. Mattis Avenue will be closed to all traffic during construction. Motorists are directed to follow the detour route around the project. Access to Carle Clinic…
(Read the Rest…)

Hollycrest Drive Closure

As part of the City’s 2015 Concrete Street Maintenance Project, it will be necessary to close Hollycrest Drive at 1105 Hollycrest Drive. The closure will begin Monday, June 15 at 7 a.m. and will last until approximately 6 p.m. on June 15, 2015, weather permitting. Emergency vehicles may approach the closure from either the north…
(Read the Rest…)

Russell Street Closure

In order to perform new storm sewer installations, Duce Construction will close Russell Street on both sides of Green Street.  Local traffic on Russell Street will be able to access Russell Street from Healey Street to the north and John Street from the south.  Green Street will remain open to traffic and will not be…
(Read the Rest…)