City of Champaign News

A warrant has been issued for the arrest of EDUARDO GUERRO CORTEZ, for Aggravated Battery, a Class Three Felony, with a bond of $1,000,000. Eduardo Guerro Cortez is a suspect who is sought in the alleged abduction of MONICA RAMIREZ, 19, of Champaign. The abduction occurred at Market Place Mall yesterday at approximately 4:05 p.m….
(Read the Rest…)

Neighborhood Code Compliance received a complaint of a dangerous tree in the 800 block of West Maple on Friday, May 23, 2014. The complainant stated they thought the tree had been hit by lightning causing a large limb to crack. Code Compliance Manager David Oliver reviewed the tree and confirmed the limb was broken but…
(Read the Rest…)

Greg Skaggs and Kevin Jackson met with Calvin Williams, the Chairman for the Committee on Construction at the Illinois Black Chamber of Commerce.  The discussion centered around strategies for the Bristol Place Demolition Policy that would allow the greatest opportunities for MBE/WBE businesses to participate.  Mr. Williams was briefed on the discussions that NSD staff…
(Read the Rest…)

The Champaign Police Department is currently investigating a reported abduction that occurred just outside the North-East entrance to JC Penney at Market Place Mall yesterday at approximately 4:05 p.m. Champaign Police responded and learned that the 19 year-old female victim was outside Market Place with another 22 year-old male friend when they were approached by three male…
(Read the Rest…)

Recently, both the Champaign and Urbana Police Departments (IL) have responded to multiple calls for service involving apparent heroin or other drug-related overdoses. Two of the Champaign calls involved drug-related deaths and two were for overdoses. According to Urbana Police Chief Patrick Connolly, Urbana officers have also noted a significant increase in the number of…
(Read the Rest…)

Schomburg & Schomburg Construction, Inc. has completed the sidewalk repair on the East side of Elm Street from Healey Street to White Street. The first two blocks of the Elm Street brick repair is complete and work is progressing on the final block between Union Street and White Street. Work in the North Campus TIF…
(Read the Rest…)

Fourth Street As part of the City’s Annual Concrete Street Maintenance Project, Beniach Construction will continue working on Fourth Street from Bradley Avenue to East Vine Street. Fourth Street will remain open for two-way traffic. The work involves pavement patching, sidewalk repairs and lawn restoration. Fourth Street is scheduled to be completed by July 31,…
(Read the Rest…)

A&R has completed all patching, routing, and sealing in the Intermodal Parking Lot. The installation of new pavement markings is the only major work item yet to be completed. Weather permitting, new parking markings will be applied this week, and the lot will be fully accessible to customers by the end of this week.  

A&R Mechanical Services, Inc. has continued to work at the intersection of Sixth St. and Healey St. They have completed reconstruction of the northeast corner of the intersection, and they should finish reconstruction of the west half of the intersection this week. A&R is also nearly done reconstructing the east half of 500 block of…
(Read the Rest…)

Rain has slowed the earth excavation phase of the project. Stark Excavating has completed approximately 50% of the basin construction. With good weather, Stark will quickly get back to work and complete the project on time. The project is scheduled to be completed by the end of this year.