120 North First Street Renovation Update
The renovation of 120 North First Street has begun. On March 7th staff extended the Redevelopment Incentive Program grant agreement for the project with a completion date of September of this year. The first step is demolishing an old rear addition and constructing a new addition. The demolition of the old addition has begun and the new addition must be complete by May 15th according to Mr. Davidson’s RIP extension agreement.