Items tagged: approaches

Windsor Road Interstate 57 Approaches

The City of Champaign would like to announce the opening of Windsor Road from Fields South Drive to Briar Hill Drive at 3 p.m. on Friday, August 15, 2014. The project is within budget and the road is open on schedule. Landscaping and miscellaneous work items will continue through to the contract completion date of October […]


Windsor Road Project

The State of Illinois awarded a contract to Stark Excavating to widen the approaches to the bridge on Windsor Road over I-57. Construction began on April 1. The road will be open to traffic on August 15, 2014. Construction will be completed by October 15, 2014. Stark is installing storm sewers on the east of […]


Windsor Road Project

Stark Excavating was awarded the City project that would widen the approaches to the bridge on Windsor Road over I-57. Construction began on April 1 and will be complete on October 15, 2014. Windsor Road will be open for traffic on August 15, 2014. Stark has completed construction of the retaining walls on the west […]