Healey Street Construction Update

A&R Mechanical Services, Inc. continues to work at the intersection of Healey Street and Fifth Street. Last week, it was discovered that UC2B’s contractor had direction bored through the UCSD sanitary sewer interceptor at two separate locations. The sewer repair slowed A&R’s progress at this location and has delayed opening the intersection to traffic to […]


Healey Street Construction Update

Last week, A&R Mechanical Services, Inc. finished reconstructing the intersection of Healey St. & Sixth St., and the intersection was fully opened to traffic.   By the end of this week, A&R will complete the reconstruction of Healey St. between Fifth St. and Sixth St. On Wednesday, June 25, A&R closed the intersection of Healey St. […]


Bradley Avenue Lane Closure

In order to perform a pole replacement and aerial electric work for Ameren Illinois, PAR Electric will be closing one westbound lane of Bradley Avenue between Willis Avenue and McKinley Avenue. The lane closure will occur on Wednesday, June 25 and Thursday, June 26, 2014 from 8 a.m. to 4:30 p.m. Westbound traffic will be reduced to […]


Healey Street and Fifth Street Road Closure

On Wednesday, June 25, 2014, A&R Services will close the intersection of Healey Street and Fifth Street. The work will consist of storm sewer improvements, new curb and gutter, new pavement, and new sidewalk. Weather permitting, work will be completed by Friday, October 17, 2014. Please pay close attention to construction signs and traffic control […]


2014 Concrete Street Maintenance Project – Phillips Drive Lane Closure

As part of the City’s 2014 Concrete Street Maintenance Project, the pavement on Phillips Drive from Nelson Court to the railroad tracks will be rehabilitated. The City’s contractor for the project is Beniach Construction. Beginning Tuesday, June 17, Phillips Drive will temporarily become a one lane, one way street south-bound from Nelson Court to Washington Street.  […]


Infrastructure Maintenance Construction Update

Schomburg & Schomburg Construction, Inc. has completed the sidewalk repair on the East side of Elm Street from Healey Street to White Street. The first two blocks of the Elm Street brick repair is complete and work is progressing on the final block between Union Street and White Street. Work in the North Campus TIF […]


Healey Street Construction Update

A&R Mechanical Services, Inc. has continued to work at the intersection of Sixth St. and Healey St. They have completed reconstruction of the northeast corner of the intersection, and they should finish reconstruction of the west half of the intersection this week. A&R is also nearly done reconstructing the east half of 500 block of […]


Washington Street Drainage Improvements

Rain has slowed the earth excavation phase of the project. Stark Excavating has completed approximately 50% of the basin construction. With good weather, Stark will quickly get back to work and complete the project on time. The project is scheduled to be completed by the end of this year.